West Broadway- Doyle is currently working on restoring waterline trenches and pavement.

East Broadway- Some of the storm water materials have arrived, the remaining materials are scheduled to arrive today. C.E Williams will begin putting the new strom drain in Monday, September 9th. They will begin work at the Carlisle Street intersection, and then move to the Old Harrisburg intersection.
After all the new storm water drains are installed, C.E Williams will begin installing the new curbing.