GETTYSBURG, PA – Beginning Tuesday, September 5, park roads west and north of Gettysburg (Day 1 Battlefield) and the East Cavalry battlefield will be repaved. This three-month project will address road surfaces and parking areas that are at the end of their lifespan.  

Road closures during this phase of paving will largely occur at night from 6 p.m. to 6 a.m., Sunday to Thursday. Friday will be held as a rain date.  

Paving Schedule Graphic August 29 update

These closures may temporarily interrupt the ability to visit portions of the battlefield while work is ongoing. No work will occur on weekends or federal holidays.  

Roads to be repaved at night from 6 pm to 6 am, Sunday to Thursday (Friday will be held as a rain date) include: 

  • Oak Ridge parking area: September 5-7, with striping to follow. 
  • Eternal Light Peace Memorial parking area: September 5-8 and 10-14 (Friday work is required due to the Labor Day federal holiday), with striping to follow. 
  • North Confederate Avenue: September 14-18, with shoulder work to follow. 
  • Doubleday/Wadsworth Avenues: September 18-20, with shoulder work to follow. 
  • Buford Avenue: September 20-22, with shoulder work and striping to follow. 
  • Reynolds Avenue: September 22-26, with shoulder work and striping to follow. 
  • West End Guide Station parking area: September 26-27, with striping to follow. 
  • Stone/Meredith Avenues: September 27-29, with shoulder work and striping to follow. 
  • Howard Avenue: September 29 to October 4, with shoulder work and striping to follow. 
  • Jones-Battalion Avenue: October 4-5. 

The roadwork at East Cavalry battlefield will occur during the day and will require full closures. 

  • United States Calvary Avenue: October 16-23. 
  • Confederate Calvary/Gregg Avenues: October 23 to November 9. 

Scheduled paving dates are subject to change due to weather or other impacts. Every effort will be made to complete the work as expeditiously as possible as well as minimize disruptions for park visitors. Full details on the schedule of road work will be made available on the park website and social media platforms as details become available. 

www.nps.gov 

About the National Park Service. More than 20,000 National Park Service employees care for America’s 424 national parks and work with communities across the nation to help preserve local history and create close-to-home recreational opportunities. Learn more at [http://../www.nps.gov]www.nps.gov, and on FacebookInstagramTwitter, and YouTube.  

Comments must include your first and last name and an email address for verification.

Click here to view our comments policy

Click here to view all comments

Subscribe
Notify of
guest
0 Comments
Newest
Oldest Most Voted
Inline Feedbacks
View all comments
0
Would love your thoughts, please comment.x
()
x