King and Culp Street Update – August, 1, 2019

 

080119 1137 KingandCulp1

080119 1137 KingandCulp1

King Street- The grading of King street will be completed today. We will begin paving Moday (8/5) or Tuesday (8/6).  The entire street will be CLOSED.

Culp Street- The milling of the first block of Culp street will be completed today (7/24), and ready to be paved. The first block will be CLOSED.

Charles Stangor

Charles (Chuck) Stangor is Gettysburg Connection's Owner, Publisher, and Editor in Chief. I would like to hear from you. Please contact me at cstangor@gettysburgconnection.org.

>