The King Street Stormwater Project has begun.
King Street will see stormwater infrastructure replacement.
The stormwater infrastructure replacement will take 2-3 weeks, followed by curb ramp replacement from May 20 to July 18.
Milling and restoration of street pavement will be completed from July 18 to August 12, which will include the first block of Culp Street.
Expect road closures and delays on King and any adjoining streets